Updates on the progress of the building of the Chabad of Henderson Mikvah
It has been a long journey for Chabad of Henderson, but we have set our roots into the ground of our new home.
- February 25th................... Construction starts!
- March 6th.......................... Mikvahs dug in the ground
- March 9th.......................... Holes are prepared for frame installation
- March 12th........................ Frames begin installation for cement
- March 19th........................ Frames installed and set
- March 26th........................ Cement for Mikvahs poured
- March 27th........................ Frames removed from Mikvahs
- April 1st - 20th................... Plumbing lines and electrical lines installed
- April 20th.......................... Cement poured for floor
- April 22nd.......................... Frame for building starts to go up
- April 26th........................... Frame is finished, construction of building begins
- May 5th............................. Internal construction continues
- May 8th............................. Work on the roof
- May 11th........................... Building base walls and doors / construction of Keilim Mikvah
- May 14th........................... Preparation for stucco application to outside of building
- May 26th............................Drywall installed
- May 27th............................Exterior stucco applied
- June 5th.............................Spackle applied to interior walls
- June 10th...........................Exterior stucco finished
- June 11th............................Interior work continues
- June 12th...........................Exterior steps built
- June 14th...........................Interior steps for Mikvah built
- June 16th...........................Cement poured for interior Mikvah steps
- June 24th...........................Outside fencing and stair rails installed
- July 10th.............................Phase One Complete
Check back in to see how it's going and don't forget to check out the mikvah PHOTO ALBUM !